Block 1
This week has been very productive with our roofers working through the wind of the first few days to get the felt and battens on and load the tiles out for laying. A couple of weeks will see the roof complete. This will leave our Plumber to fit the Gutters and Rain Water Pipes.
Blocks 2 & 3
The external stone work is up past first floor, and the internal walls have been erected ready for First Fixing the M&E.
Next week will see an increase in activity with internal works starting on Block 1 and First Fix kicking off in Blocks 2 & 3.