Friday, 15 March 2013

Block 1

This week has been very productive with our roofers working through the wind of the first few days to get the felt and battens on and load the tiles out for laying. A couple of weeks will see the roof complete. This will leave our Plumber to fit the Gutters and Rain Water Pipes.


Blocks 2 & 3

The external stone work is up past first floor, and the internal walls have been erected ready for First Fixing the M&E.


Next week will see an increase in activity with internal works starting on Block 1 and First Fix kicking off in Blocks 2 & 3.

Friday, 8 March 2013

Block 1

The Timber Kit has been erected ready for the roof to start which is schedule for Monday. Windows will follow on hopefully making the buildings water tight in a few weeks.

Block 2 and Block 3

Roof on, windows in and the external stone work up to first floor, internal plaster boarding has been started and the acoustic floor has been laid.
  
Next week will see an increase in the workforce on site to get Block 1 Roofed and start internal stud walls to get the plots ready for 1st Fix M&E.