Monday, 22 April 2013

Works have progressed steadily on site and we have managed to strip the majority of our scaffold on our 2 single blocks and complete the render to reveal the buildings.

Block 1

The Stonework is nearing completion and our scaffold is due to be taken down on the front early next week to allow excavation of service trenches. Next week should also see the return of our Ground Workers to start completing the externals, by shaping the road, laying kerbs and flagging around plots.

Block 2 with scaffold stripped and render complete


Internally we are skim complete in Blocks 2 & 3, in 4 plots we have started the completion items, we have Mist coated and installed 2nd fix M&E and kitchens are being fitted.


Monday, 8 April 2013

The weather has finally improved and has enabled us to make good progress on site. The roof is complete and works have started on the external stone work and we are already at the 1st fix stage upstairs.


The stone work on Blocks 2 & 3 has been completed and we have partially stripped the scaffold, leaving enough to allow the renderers to work off. Internally we have completed our 1st fix in all 4 plots and have closed up and skimmed in Block 2.


Next week should see the Dryliners complete the perimeter boarding and internal walls leaving the plots ready for the follow on trades who are all lined up and ready to go.