The weather has finally improved and has enabled us to make good progress on site. The roof is complete and works have started on the external stone work and we are already at the 1st fix stage upstairs.
The stone work on Blocks 2 & 3 has been completed and we have partially stripped the scaffold, leaving enough to allow the renderers to work off. Internally we have completed our 1st fix in all 4 plots and have closed up and skimmed in Block 2.
Next week should see the Dryliners complete the perimeter boarding and internal walls leaving the plots ready for the follow on trades who are all lined up and ready to go.