Monday, 21 January 2013

This is another site that has been affected by the cold weather conditions this week, with concrete screeds to the floor slabs being delayed.

The timber frame kits have been ordered to be delivered to site in the next couple of weeks, and once they start to get erected the site will soon start to take on the look of a housing development.

Scaffolds to the 2 smaller plots will be starting in the next week, which allows access for the timber frame installers to fix the kits together, and soon after the roof coverings will be starting.

Hopefully the cold temperatures will be short-lived so that any affect on the works will be minimal and the construction can progress and take shape as rapidly as planned!